The end of the Mechanics’ Lien Act

Kenneth McCullogh, QC and Conor O’Neil, P.Eng.

On December 18, 2020, the Legislative Assembly of New Brunswick passed the Construction Remedies Act. The new legislation will not take effect until a date to be named at which time it will replace the existing Mechanics’ Lien Act (“Act”). The new legislation is lengthy and technical in nature compared to its predecessor. As anticipated the new Act does not include provisions for prompt payment or adjudication which have been passed in other provinces, although the door has been left open for such provisions at a later date.

Modernization of the Act

Many of the changes will be familiar to those who work in jurisdictions outside New Brunswick. As in almost all other provinces, the statutory holdback amount which is required to be retained by an owner will be reduced from 15% of the contract price to 10%.

Similarly, the time within which a lien holder has to register its claim for lien will be harmonized to a single 60 day period. In most instances that 60 day period will run from the earliest of the date of certification of substantial performance, completion, termination or abandonment of the contract. Importantly for subcontractors, the time period will also be triggered by the date upon which the subcontractor last supplied services or materials to the improvement. This provides clarification for certain subcontractors, for example earthworks, who supply their services early in a project and do not stay on for the entire life cycle.

A subtle, but significant, new change will be that parties can no longer contract out of their lien rights. The new legislation specifically provides that every contract or subcontract is deemed to be amended to conform to the new Act.

Substantial performance and completion of projects

The new Act offers some clearer direction for determination of when a contract is substantially performed and completed. As to substantial performance, the test that the improvement be ready for use or the purpose intended is codified; however, a second criteria will be in place which requires that the improvement be capable of completion or that the remaining defects be less than a certain amount, for which the new Act provides a formula. Similarly, completion requires that the cost of completing the improvement be less than 1% of the contract price.

The Construction Remedies Act will more strictly limit who can perform the role of payment certifier to an architect, engineer or a third party designated in the contract. A contractor will have the ability to directly request that the payment certifier determine if the contract is substantially performed. The new Act also prescribes times within which the payment certifier will deliver its certificate. Finally, the contractor will be required to post the certificate of substantial performance at the site of the improvement. The new Act leaves open the possibility that other forms of notice may be prescribed by regulation. The government has previously signaled that it would be preferable if an industry association take on the role of publishing certificates of substantial performance online, as is done in trade publications in some other jurisdictions. This would have the effect of providing more timely and consistent notice to subcontractors and suppliers that the clock is ticking for the release of holdback and expiration of lien rights on projects.

Where a contract is substantially performed and some services or materials remain to be supplied, the owner will be required to maintain a finishing holdback. The finishing holdback applies to the amount which remains to be completed after substantial performance, representing 10% of that amount. The finishing holdback may be released 60 days after the completion, abandonment or termination of the contract.

Release of holdback after the lien period expires will become mandatory, rather than permissive. Owners and payment certifiers that have in the past converted the statutory holdback to a deficiency holdback after the period for registration of a claim for lien has expired will no longer be able to do so. Owners will want to carefully keep track of such amounts to avoid the issue of not retaining enough funds to complete a project. For longer projects the Construction Remedies Act also provides that holdback may be released on an annual or phased basis.

Trust accounts and breach of trust

The trust provisions of the new lien legislation will be significantly altered. The obligations of owners, in particular, will greatly expand. As was always the case, the contractor and subcontractor trusts remain.

Funds in the hands of an owner will become trust funds when the funds become payable to the contractor. Owners will also be required to establish a holdback trust account for such funds with their financial institution in an account separate and apart from other funds for the project. This account is to be administered, in most cases, by the owner and the contractor. Any payments made out of the holdback trust account require the signature of each of the trustees and trustees are required to maintain records to ensure that the funds are traceable.

Finally, a breach of the trust provisions remains an offence under the Provincial Offences Procedures Act; however, directors, officers and any person who has effective control of the corporation that assents to, or acquiesces in conduct that the person knows, or reasonably ought to know, would result in a breach of trust may be liable for such a breach. This means trustees may be personally sued in the Court of Queen’s Bench for breach of trust by beneficiaries of the trust.

What’s next

Government is now drafting regulations under the Construction Remedies Act and it is not anticipated that the Act will come into effect until the regulations are complete.

For the time being the Mechanics’ Lien Act continues to apply to all construction projects in New Brunswick. When the transition happens, the new legislation provides that contracts entered into after the Construction Remedies Act comes into force will be governed by the new legislation. There will be a period of grandfathered contracts as the Mechanics’ Lien Act will continue to apply to any contracts which are entered into before the date upon which the Construction Remedies Act comes into force.


This update is intended for general information only. If you have questions about how the information above may affect you, please contact any member of our construction group.

SHARE

Archive

Search Archive


 
 

IRCC expands authorization for foreign workers to study without a study permit: Four things you need to know

July 13, 2023

By Sara Espinal Henao Immigration, Refugees and Citizenship Canada (“IRCC”) has announced a promising new temporary measure that allows foreign workers to study for a longer duration without a study permit, opening the door for…

Read More

Canada’s first-ever Tech Talent Strategy announced

July 12, 2023

By Brendan Sheridan The Government of Canada recently announced a number of aggressive immigration measures to help attract top talent to Canada in high-growth industries in an effort to fuel innovation and drive emerging technologies.…

Read More

ESG and dispute resolution: fighting for greener ways

July 5, 2023

By Daniela Bassan, K.C. All stakeholders in the legal profession, including litigators, have a shared interest in promoting environmental, social, and governance (ESG) pathways towards building a greener society. It is crucial for litigators to…

Read More

Amendments to the Canada Business Corporations Act affecting registers of individuals with significant control

June 30, 2023

By Kimberly Bungay and Colton Smith Since June of 2019, corporations formed under the Canada Business Corporations Act have been required to prepare and maintain a register of individuals with significant control (an “ISC Register”).…

Read More

Navigating the waters: Compliance with multiple regimes

June 22, 2023

By Kim Walsh and Olivia Bungay Compliance with Russian sanctions goes beyond complying with Canada’s Russia Regulations. Canadian individuals and businesses may be unaware of several other sanctions regimes that apply to them. In conjunction…

Read More

Nova Scotia releases offshore wind roadmap

June 21, 2023

By David Randell, Robert Grant, K.C., Sadira Jan, and James Gamblin On June 14, 2023, the Province of Nova Scotia released the first of three modules (the “Module”) which will comprise the Nova Scotia Offshore…

Read More

Board, Bye!: Changes to the Municipal Appeal Process under the Urban and Rural Planning Act, 2000

June 19, 2023

By: Joe Thorne, Giles Ayers, and Jayna Green Introduction Prior to June 1, 2023, decisions made by municipal town councils in Newfoundland and Labrador could be appealed to one of four Regional Appeal Boards pursuant…

Read More

Navigating Canada’s sanctions against Russia: New guidance on ownership and control of an entity

June 16, 2023

By Kim Walsh and Olivia Bungay Canadian sanctions targeting Russia in relation to Russia’s ongoing invasion of Ukraine were significantly expanded over the past year. Critical to compliance with Canada’s sanctions targeting Russia, individuals and…

Read More

Navigating Canada’s economic sanctions against Russia

June 6, 2023

By Kim Walsh and Olivia Bungay Canadian sanctions targeting Russia in relation to Russia’s ongoing invasion of Ukraine were significantly expanded over the past year. The Special Economic Measures (Russia) Regulations impose sanctions on individuals…

Read More

Federal Government introduces amendments to expand the mandates of the two historic Atlantic Accord Acts to include offshore wind energy

June 1, 2023

David Randell, Sadira Jan, Robert Grant, K.C., Greg Moores, G. John Samms, and James Gamblin The recent tabling of federal legislation is an important step for offshore wind development in the offshore areas of Nova…

Read More

Search Archive


Scroll To Top