Client Update: Mechanics’ Lien Act reform

The Legislative Services Branch of the Province of New Brunswick has announced in issue 40 of the Law Reform Note, available online, its intention to reform the Mechanics’ Lien Act. The Note draws on similar legislative amendments that have been undertaken by other provinces, including most recently Ontario’s overhaul of its Construction Lien Act, which passed through the Legislative Assembly of Ontario late last year but will come into force on a date yet to be named.

Major changes to core elements of the Act are not planned; however, there are some significant proposed changes that are similar in scope to those implemented in Ontario and elsewhere. The Note primarily focuses on modernizing the Act to reflect changes in similar legislation across the country. A second note is expected to be released later this year which will deal with proposed amendments pertaining to prompt payment and dispute resolution.

Modernization of the Act

Modernization of the Act involves a number of amendments relating to liens, holdbacks, trusts, and surety bonding. The following changes are being considered:

  • Amending the definition of “improvement” to include “fixtures”.
  • Amending the definition of “owner” to reflect the commercial realities of the public-private-partnership model, where the owner may not clearly fall within the current definition.
  • The Act currently provides that the time within which a lien may be preserved is different for some parties (i.e. suppliers, equipment rentals or contractors). It has been recommended that the period be 60 days for all lien holders.
  • Adding “termination” as a triggering event for the time within which a lien holder must preserve its claim for lien.
  • Amending the rules and requirements for vacating claims for lien.
  • Prescribing how lien claims are to be filed against subdivisions, condominiums, and leaseholders.
  • Adding a requirement for suppliers to construction sites to provide actual notice to the owner of an intent to assert a lien. It is unclear whether this requirement would be limited to residential construction or would extend to all construction projects.
  • Reducing the statutory holdback from 15% to 10%, which is in line with the holdback provisions of almost all other provincial lien legislation.
  • Amendments to more clearly define the terms completion and substantial completion for the purposes of the time limits imposed by the Act. This reflects changes most recently made to Nova Scotia’s lien legislation.
  • Adding new provisions dealing with release of holdback mechanisms including early, phased, and segmented release of holdback. It is also suggested that the release of holdback be made mandatory rather than permissive, as is now the case.
  • Strengthening the trust provisions, including extending the provisions to include owners’ and vendors’ trusts.
  • Two options are discussed for protection of trust funds, particularly in the event of insolvency: (1) segregating holdback funds; or (2) enhanced record-keeping requirements. A third option, project bank accounts, is mentioned but not discussed at length. It is acknowledged that any of the options would create a more significant administrative burden on payors.
  • Expanding the right to information under section 32 of the Act.
  • Contracting parties may be permitted to opt out of the holdback and lien scheme where labour and material payment bonds are in place. If this is adopted, New Brunswick would be the first Canadian jurisdiction to have such a scheme in place.
  • Further penalties or an enforcement mechanism might be added to the Act to discourage non-compliance.

Prompt payment and dispute resolution

Prompt payment and changes to dispute resolution under the Act are briefly touched on in the Note; however, a second note from the Legislative Services Branch will set out more detail on these topics later this year.

Prompt payment legislation is in place in several other common law countries and is likely to be introduced in other jurisdictions in Canada now that Ontario has set out the prototype. Importantly, the Federal government is likely to introduce its own form of prompt payment legislation respecting construction contracts.

Ontario’s legislation includes some technical changes to its dispute resolution provisions, the most significant of which is the introduction of an adjudication model described as “pay now, argue later”. Adjudicators are nominated through a central Authorized Nominating Authority, which is responsible for development and overseeing training programs for adjudicators. Parties to a dispute would be empowered to refer it to adjudication respecting any of the following matters:

  1. The valuation of services or materials provided under the contract.
  2. Payment under the contract, including in respect of a change order, whether approved or not, or a proposed change order.
  3. Disputes that are the subject of a notice of non-payment.
  4. Amounts retained as set-offs.
  5. Payment of a holdback.
  6. Non-payment of holdback.
  7. Any other matter that the parties to the adjudication agree to.

The goal of adjudication is to fast-track disputes with interim decisions from an adjudicator within 39-60 days with a view to keeping a project moving. Parties are free to re-visit disputes at the conclusion of the project.

Draft amending legislation is not expected for some time. However, owners, contractors, subcontractors, suppliers, design professionals and others in the construction industry should keep abreast of this initiative and consider how the possible amendments could affect their commercial relationships going forward. Stakeholders have been invited to submit their comments on the Note to the Legislative Services Branch by February 15, 2018. The Legislative Services Branch contact information is:

Legislative Services Branch, Office of the Attorney General
Chancery Place, P.O. Box 6000, Fredericton, N.B., Canada E3B 5H1
Tel: 506.453.2855, Email: lawreform-reformedudroit@gnb.ca

This update is intended for general information only. If you have questions about how the information above may affect you, please contact any member of our construction group.

SHARE

Archive

Search Archive


 
 

New Brunswick Provincial Government releases Climate Change Plan

October 11, 2022

By Alanna Waberski and Isaac McLellan On September 21, 2022, the Government of New Brunswick released its renewed climate change action plan which aims to help the province adapt to climate change while steering New…

Read More

Court upholds mandatory vaccine policy – Placing employee on unpaid leave not constructive dismissal

October 3, 2022

Mark Tector and Ben Currie While there have been a number of arbitration decisions on the subject, Parmar v Tribe Management Inc., 2022 BCSC 1675 appears to be the first reported civil court decision to…

Read More

Federal Government, Nova Scotia, and Newfoundland and Labrador clearing the way for offshore wind development

September 29, 2022

Sadira Jan, Dave Randell, and James Gamblin Nova Scotia (“NS”) and Newfoundland and Labrador (“NL”) are positioned to become international leaders in offshore wind and green hydrogen. Each province has expansive offshores areas, abundant wind…

Read More

Health Canada announces legislative review of Cannabis Act

September 27, 2022

Kevin Landry and Nikolas Shymko The Cannabis Act came into force on October 17, 2018, putting in place framework for controlling the sale, possession, production and distribution of cannabis. The Cannabis Act requires the Minister…

Read More

COVID-19 immigration and travel: where are we now?

September 27, 2022

Brendan Sheridan and Brittany Trafford. Many events and workplaces started to feel more normal over the summer as we emerged from over two years of restrictions and COVID-19 pandemic precautions. However, as people line up…

Read More

Deadline extended on CAPSA guideline consultations

September 21, 2022

By Level Chan and Shaniqwa Thomas The Canadian Association of Pension Supervisory Authorities (CAPSA) has extended its deadline for submissions to October 14, 2022 on the following draft guidelines: Approach to Risk Management Guideline; Environmental,…

Read More

An email scam cautionary tale

September 16, 2022

By Nancy Rubin, K.C. and Levi Parsche What happens if a person accidentally makes payment to a hacker, instead of to the person they actually owe money? Should they have to pay again? In the…

Read More

Federal holiday declared to honour Queen’s death on September 19, 2022, but Atlantic provinces divided on whether to declare the holiday for private sector businesses

September 14, 2022

G. Grant Machum and Ben Currie On Tuesday, September 13, 2022, Prime Minister Justin Trudeau declared a federal holiday on Monday, September 19, 2022 to honour the death of Queen Elizabeth II. Minister of Labour…

Read More

Shareholder Agreements in Nova Scotia

September 13, 2022

Kevin Landry, Matt Jacobs Shareholder agreements are a key part of corporate governance. Nova Scotia is unique from other Canadian jurisdictions because the Companies Act (Nova Scotia) doesn’t contemplate ‘Unanimous Shareholder Agreements’ as other corporate…

Read More

Overwhelming backlog of Canadian immigration applications prompts new government action

August 25, 2022

By Kathleen Leighton Last year, Canada boasted record admissions of permanent residents, despite the COVID-19 pandemic, and has an even more ambitious target for 2022 – namely, to welcome 431,000 permanent residents to the country.…

Read More

Search Archive


Scroll To Top