Skip to content

Business interruption insurance: recent decision may impact whether COVID-19 disruptions are covered

Colin D. Piercey, Joe Thorne and Sam Ward

On March 25, 2020, we published an update setting out considerations for businesses impacted by the COVID-19 pandemic. In particular, whether business interruption may respond to these types of losses, and what questions a business should ask when considering whether to make a business interruption claim with its insurer.

Our previous update can be found here.

In our previous update, we noted that most business interruption policies will require that three conditions be met in order to trigger coverage: (1) direct physical loss or damage; (2) of covered property; (3) resulting from a covered cause of loss.

The requirement that there be “direct physical loss or damage” has been seen as a barrier to a claim arising from the COVID-19 pandemic.

However, a recent decision from the Ontario Superior Court of Justice may lower the threshold for a business interruption insurance claim for COVID-19-related closures.

In MDS Inc. v. Factory Mutual Insurance Company,[1] released March 30, 2020, the Court concluded that:

  • “Physical damage” may be interpreted broadly to include “impairment of function or use of tangible property”;
  • This may be the outcome even where there is no actual physical damage to the covered property.

While this decision was highly fact-specific, was not decided in the context of a COVID-19 claim and resulted from a leak of heavy water at a nuclear facility, it does offer a potential avenue for business interruption claims during the pandemic.

The decision

The Plaintiffs, MDS Inc. and MDS (CANADA) Inc. (together, “MDS”), purchased and sold radioactive isotopes produced by Atomic Energy of Canada Limited (“AECL”) at AECL’s facility. On May 14, 2009, a leak of heavy water at AECL’s facility led to a 15-month shutdown as ordered by the Canadian Nuclear Safety Commission.

MDS had an “all-risks” policy against “losses from all risks of physical loss or damage except as excluded” (the “Policy”) issued by the Defendant insurer, Factory Global Mutual Company (“Factory Mutual”). The Policy included coverage for such losses arising from damage to a supplier’s property, including AECL.

MDS submitted a loss of profits claim to Factory Mutual totalling $121,248,000. Factory Mutual denied the claim because, among other things, the water leak did not cause actual physical damage to AECL’s property.

One of the issues before the Court was the interpretation of “physical damage” in the Policy. MDS argued that “physical damage” should include loss of use of the property despite no actual damage. Factory Mutual argued that the Policy should be interpreted narrowly to require actual physical damage.

The Court reviewed cases interpreting “physical damage” in Canada and the US and concluded that there was not one single determinative definition of that term applicable to the Policy.

The Court determined, however, that there were cases that indicated that “physical damage” in the insurance policy context was broader than just actual physical damage to property.

Applying those cases, the particular provisions of the Policy, the facts of the MDS claim, and the principles of contractual interpretation, the Court concluded:

In assessing the objective reasonable expectation of the parties as to the meaning of physical damage, it makes common sense that if the unanticipated leak of heavy water…precipitates the shutdown…ordered by CNSC….that this circumstance….would constitute resulting physical damage

…I conclude that a broad definition of resulting physical damage is appropriate in the factual context of this case to interpret the words in the Policy to include impairment of function or use of tangible property caused by the unexpected leak of heavy water.

This interpretation is in accordance with the purpose of all-risks property insurance, which is to provide broad coverage.  To interpret physical damage as suggested by the Insurer would deprive the Insured of a significant aspect of the coverage for which they contracted, leading to an unfair result contrary to the commercial purpose of broad all-risks coverage.

While there were US cases before the Court where contamination did not rise to the level of “physical damage”, they were found to be distinguishable on the basis that, in those cases, the contaminated premises were still considered usable, whereas the leak at AECL’s facility required it to be shut down.

What it means for you

As set out above, this case was highly fact-specific and was decided on the provisions of the Factory Mutual Policy and the facts of the case. Every claim against an insurance policy will turn on such considerations.

While there was a precipitating event namely the leak of heavy water that resulted in the ordered shutdown, this decision does indicate that our courts may take a broader view of “physical damage” as a usual precondition for business interruption claims.

The COVID-19 pandemic has had a huge and wide-reaching impact on business across Canada. Many businesses have had access to their bricks-and-mortar operations reduced or eliminated either by government decree or by social distancing in general.

Coverage still might not be available to those businesses that have not been forced to close entirely. The fact that AECL’s facility had to be shut down was significant to the Court’s decision in this case. A mere downturn in business caused by COVID-19 might not be considered an “impairment of function or use of tangible property” sufficient to rise to the level of “physical damage”.

The federal and provincial response to the COVID-19 impact on business is an evolving process. To date, the governmental focus has been on financial aid and tax relief. However, there have been laws passed in US states mandating that insurers provide retroactive coverage for COVID-19 business interruption losses. Whether such laws may be considered in Canada remains to be seen.

Any business holding a form of business interruption insurance should review their policy and consider seeking legal advice about a potential claim for COVID-19-related disruptions to their operations.

[1] 2020 ONSC 1924.


This article is provided for general information only. If you have any questions about the above, please contact a member of our Insurance Group.

Click here to subscribe to Stewart McKelvey Thought Leadership articles and updates.

SHARE

Archive

Search Archive


 
 

TTC’s Random Testing Decision: A Bright Light for Employers in the Haze of Marijuana Legalization

April 11, 2017

Rick Dunlop In my December 15, 2016 article, Federal Government’s Cannabis Report: What does it mean for employers?, I noted the Report’s1 suggestion that there was a lack of research to reliably determine when individuals are impaired…

Read More

Unionization in the Construction Industry: Vacation Day + Snapshot Rule = Disenfranchisement

April 4, 2017

Rick Dunlop and Michelle Black On March 14, 2014, CanMar Contracting Limited (“CanMar”) granted a day off to two of its hard working and longer serving employees so they could spend time with their respective families. That…

Read More

Sometimes a bad deal is just a bad deal: unconscionability and insurance claim settlements in Downer v Pitcher, 2017 NLCA 13

March 16, 2017

Joe Thorne and Meaghan McCaw The doctrine of unconscionability is an equitable remedy available in exceptional circumstances where a bargain between parties, be it a settlement or a release, may be set aside on the basis that…

Read More

Privilege Prevails: Privacy Commissioner protects solicitor-client communications

March 16, 2017

Jonathan Coady After more than five years, the Prince Edward Island Information and Privacy Commissioner (the “Privacy Commissioner”) has completed her review into more than sixty records withheld by a local school board on the…

Read More

The Latest in Labour Law: A Stewart McKelvey Newsletter – Nova Scotia Teachers Union & Government – a synopsis

March 7, 2017

Peter McLellan, QC & Richard Jordan Introduction On February 21, 2017 the Nova Scotia Government passed Bill 75 – the Teachers’ Professional Agreement and Classroom Improvement (2017) Act. This Bulletin will provide some background to what is, today,…

Read More

Scotia Mortgage Corporation v Furlong: The Supreme Court of Newfoundland and Labrador weighs in on the former client rule in commercial transactions

March 1, 2017

Bruce Grant, QC and Justin Hewitt In the recent decision of Scotia Mortgage Corporation v Furlong1 the Supreme Court of Newfoundland and Labrador confirmed that where a law firm acts jointly for the borrower and lender in the placement…

Read More

The Ordinary Meaning of Insurance: Client Update on the SCC’s Decision in Sabean

February 21, 2017

The Supreme Court of Canada released its decision in Sabean v Portage La Prairie Mutual Insurance Co, 2017 SCC 7 at the end of January, finally answering an insurance policy question that had divided the lower…

Read More

Client Update: Outlook for the 2017 Proxy Season

February 8, 2017

In preparing for the 2017 proxy season, you should be aware of some regulatory changes and institutional investor guidance that may impact disclosure to, and interactions with, your shareholders. This update highlights what is new…

Read More

Client Update: The Future of Planning and Development on Prince Edward Island – Recent Amendments to the Planning Act

January 23, 2017

Perlene Morrison and Hilary Newman During the fall 2016 legislative sitting, the Province of Prince Edward Island passed legislation that results in significant changes to the Planning Act. The amendments received royal assent on December 15, 2016 and…

Read More

Plaintiffs’ medical reports – disclosure obligations in Unifund Assurance Company v. Churchill, 2016 NLCA 73

January 10, 2017

Joe Thorne1 and Justin Hewitt2 In Unifund Assurance Company v Churchill,3  the Newfoundland and Labrador Court of Appeal considered the application of our rules of court and the common law as they relate to disclosure of documents produced in…

Read More

Search Archive


Scroll To Top